Gordie Howe Bridge Opening Delayed to Fall 2025

WINDSOR, Ontario — Having delivered the busiest year of construction to date, the Gordie Howe International Bridge project team announced construction completion is now planned for September 2025 with the first vehicles expected to travel across the bridge that fall.

Originally, the $5.7 billion (CDN) project was scheduled for completion in November 2024 with opening anticipated by the end of that year. However, the project, like many others, experienced unprecedented disruptions as a result of the COVID-19 global pandemic. The disruptions were even more prevalent for the Gordie Howe International Bridge project given the differing applicable restrictions in the U.S. and Canada, combined with the ramping up of construction activities in early 2020.

“After a three-year pandemic and considering the size and complexity of the Gordie Howe International Bridge project, our project team is pleased that the impact to the construction schedule is limited to only 10 months beyond the original contracted completion date and that we could agree on a reasonable adjustment to the contract value,” said Charl van Niekerk, CEO, Windsor-Detroit Bridge Authority. “With safety as our top priority, we will continue to work together to deliver this much needed infrastructure to the thousands of eager travelers ready to cross North America’s longest cable-stayed bridge.”

Like most public-private partnerships contracts, the contract between Windsor-Detroit Bridge Authority and Bridging North America provides for the schedule and cost impacts of certain risks to be shared. As a result, WDBA and BNA have agreed to amend the contract to include the new September 2025 construction completion date, new measures to ensure this date is achieved, and an updated overall contract value of $6.4 billion (CDN).

Further, this new timeline is achievable without compromising quality and most importantly, the health and safety of our workers. The great progress made in 2023 and the ability to mitigate and manage the challenges the team has faced is a testament to the dedication of the workers and collaboration between WDBA, BNA, the State of Michigan and all project delivery partners. 

Recognizing that an extended construction period impacts the project host communities, WDBA has budgeted for a one-year extension of the Gordie Howe International Bridge Community Benefits Plan. With $3 million (CDN) to be divided equally between Canada and the US and expended over the 2025-2026 fiscal year, residents and business owners in Sandwich/west Windsor and Delray/Southwest Detroit will see positive outcomes from further regional investments. Additional details on the approach to allocating this funding will be shared later in 2024.

“We appreciate the ongoing commitment of our partners at WDBA and BNA to keeping this vital project on track during an unprecedented worldwide pandemic that presented many obstacles on both sides of the border,” said Bradley C. Wieferich, Directror, Michigan Department of Transportation. “We are especially pleased that along with a revised timeline comes a pledge for further community benefits in Southwest Detroit and BNA’s pledge to add cycling lanes to streets on the Detroit side. We saw a great deal of work completed in 2023 and look forward to opening this great bridge in 2025.”